OUR RECENT PROJECTS

Bebop_2_2019-09-11T105843+0200_2585A5_ed
36880755_2067853746590031_35550538666659
0000759807_resized_thejewelatthemarcphot

TELESURE AUDITORIUM STRUCTURAL STEEL

Aveng Grinaker LTA

Weight: 7 Tons
Value: R300 000
Duration: 1 Month

VILLAGE WALK SKYLIGHT STRUCTURAL STEEL

Aveng Grinaker JV Trencon construction

Weight: 30 Tons
Value: R 1Mil
Duration: 2 Months

129 RIVONIA VILLAGE WALK

Aveng Grinaker LTA jv Trencon Constriuction

Projects: Planet fitness running track

               MMI HVAC Platform

               Structural platform & Bondek

               Various Sundry metals

               Various Structural steel Projects

Combined Weight: 163 Tons

Value: R 5Mil

Duration: 18 Months

 
89ae3254-167d-45cd-829b-9aa10619a5d0.jpg
IMG_1325-Edit-800x533.jpg
0000795383_resized_venetiaundergroundpro

BARLOW WORLD ISANDO

Trencon Construction

Arctig was Appointed as the main Sundry Metal Sub Contractor

Weight: 32 Tons

Value: R 1Mil

Duration: 6 Months

ATTERBURY HEAD OFFICE STEEL FIT OUT

WBHO

Weight: 32 Tons
Value: R 1Mil
Duration: 6Months

VENETIA UNDERGROUND PROJECT, STRUCTURAL STEEL

BMH Africa

Weight: 165.5 Tons
Value: R 6Mil
Duration: 12 Months

 